Change requests: how scope grows after signing, and how to price it calmly

· 4-minute read · Buying software · by Direct Softworks

Every project changes after the contract is signed. What matters is whether each change becomes a priced decision or an argument about what was implied.

Week three of a build. You click through the order screen for the first time, with real products in it, and realise the warehouse also needs to see the delivery address. Nobody wrote that down, because in the old spreadsheet it was simply the column next to the client name.

That moment is not a failure of the project. It is the reason to see working software early. People find out what they need by using something, not by reading about it, and the sooner they use it, the cheaper the discovery.

The awkward part comes a second later: is that in the price?

Why scope grows, and why that is healthy

Changes come from three places. Things nobody knew until they saw a screen. Things somebody knew and did not say, usually an exception that lives in one person's head. And things that changed in the business itself: a new client with its own rules, a new warehouse, a new legal requirement.

None of those is anybody's fault, and all three will happen on any project longer than a fortnight. A plan that assumes they will not is the plan that goes wrong. Change is not the sign of a project in trouble. Unpriced change is.

Three kinds of request, and who pays for each

A correction. The written scope said it, and the delivered screen does not do it. That is not a change, it is a defect, and the supplier fixes it without a quote.

A swap. You replace something not yet built with something of similar size. Early in a build this can cost little or nothing, because no work is thrown away. Ask whether a swap is possible before assuming everything is an addition.

An addition. New behaviour the scope did not describe. That is new work, and it gets its own price.

Most disagreements are about which of the three a request is. The delivery address above could be any of them, depending on what the scope said about the warehouse. The written scope is what decides which kind a request is, which is why it has to exist before anybody starts building.

How to price a change without a fight

Write it as one paragraph. What should happen, for whom, and why. "The picking list shows the delivery address, because drivers load by route" is a request a supplier can price. "Improve the warehouse screen" is not.

Ask for a fixed number before it is built. Two numbers, in fact: money and days. A change that costs little but moves the launch by two weeks may not be worth it this month. Every change quote should say what it adds to the price and what it adds to the timeline.

Decide now, after launch, or never. Plenty of requests feel urgent in week three and irrelevant by week eight, once people are used to the screen. Keep a list, and decide each item deliberately rather than by default.

Batch the small ones. Five small changes priced together cost less to estimate, build and test than five separate ones.

Our own practice follows the same pattern: the price for the agreed scope does not move, and changes are quoted separately, fixed, before they are built. Working software appears from the second week and you click through it weekly, which is when most of these requests surface.

The changes that are not small

Some requests look like a field and are really a new assumption. A second company in the same system, a second currency, offline working: each of those touches almost every table, and deciding them late costs far more than deciding them on day one.

If a supplier quotes one of those at several times what you expected, that is usually the supplier being honest rather than opportunistic. Ask them to explain which assumption it changes. A supplier who says yes to every change for free is either padding the original price or saving the argument for the end.

Keep one list

A single shared document, one row per request: date, who asked, what, the decision, the price, the effect on the timeline, and the status. Nothing more elaborate is needed.

By the end of the project that list is the record of what you actually bought, which the original scope no longer is. It settles the question of whether something was agreed, and it gives you a ready-made backlog for the months after launch.

The general shape

Scope is going to move. The goal was never to stop it moving, only to make sure that every move is a decision somebody took on purpose, with a price and a date attached, rather than something that drifted in and got argued about later.

That is the real case for a fixed price with separately quoted changes: not that it prevents change, but that it turns changing your mind into a priced decision instead of a negotiation about what was implied.